4 Trains each comprised of:
•(1) 400GPM Amine Plant •(3) Compressors- (2) 3612 and (1) 3608 •(1) 1 MM/BTU Glycol Dehydration Package |
•(8) Pre-Fabricated Pipe Racks
•(1) Cryogenic Plant; Interconnect and Facility Integration •Electrical Area Classifications for facility |
Basile Processing facility is strategically located to provide CO2 treating and NGL processing to the local high-deliverability salt-dome natural gas storage facility. IMAGE CES was tasked with completing the turnkey engineering and design of this facility inside of 6 months. IMAGE CES met this deadline while designing the unit for optimal operational efficiency with a minimum footprint. The Client required all components to be pre-fabricated and as compact as possible. Using EDGE 360 the Client and IMAGE CES were able to optimize the layout and design to meet the Clients stringent operational requirements regarding spacing and equipment access.